PRODUCTION SCHEDULE

WEEK 1: CONCEPT

Make production schedule, develop new concept, pre-visualization storyboard, set up website.

WEEK 2: PRE-PRODUCTION/MODELING

MON, MAR 31

DUE: Assign 1, website, storyboard, production schedule.

WORK: Begin assembling animatic, develop style frames for lighting concepts and sarcophagus image, look up pyro tutorials.

TUES, APR 1

WORK: Model torch and sconce, begin modeling mummy, make shot list.

WED, APR 2

WORK: Continue modeling mummy, start sarcophagus. Complete assignments for other classes.

THURS, APR 3

WORK: Continue modeling mummy and sarcophagus.

FRI, APR 4

WORK: SIGGRAPH meeting, Botanical Gardens field trip. Continue modeling mummy and sarcophagus.

SAT, APR 5

WORK: Continue modeling mummy and sarcophagus. Complete assignments for other classes.

SUN, APR 6

Makeup day.

WEEK 3: MODELING

MON, APR 7

WORK: Continue modeling mummy and sarcophagus.

TUES, APR 8

WORK: Continue modeling mummy and sarcophagus.

WED, APR 9

DUE: Assign 2, animatic, shot list, revised production schedule.

WORK: Complete assignments for other classes.

THURS, APR 10

WORK: Atlantamation. TECH311 Project 1 Due. Drive Heather for filming. Model minor elements (broken lantern, coins, hallway, shattered vases, cobwebs, small rocks). Begin assembling texture for sarcophagus.

FRI, APR 11

WORK: Drive Heather for filming. Continue modeling minor elements and modeling/shading sarcophagus and mummy.

SAT, APR 12

WORK: Complete assignments for other classes. Finish all modeling and place objects in scene, continue shading sarcophagus/mummy.

SUN, APR 13

Makeup day.

WEEK 4: SHADING

MON, APR 14

WORK: Finish sarcophagus based on critique, continue mummy shading. Block in lighting.

TUES, APR 15

WORK: Finish sarcophagus, continue mummy shading.

WED, APR 16

WORK: Complete assignments for other classes. Continue/finish mummy shading based on critique.

THURS, APR 17

WORK: Begin shading for all minor objects.

FRI, APR 18

WORK: Laika Presentation. Continue shading minor elements. Set up 3D render passes.

SAT, APR 19

WORK: Complete assignments for other classes. Finish shading minor objects. Set up 3D render passes.

SUN, APR 20

Makeup day.

WEEK 5: ANIMATION/FX

MON, APR 21

WORK: Final touches on all textures based on critique, render breakdowns.

TUES, APR 22

WORK: Finalize midterm website documentation, render breakdowns.

WED, APR 23

DUE: Assign 3, midterm assets, documentation, breakdowns.

WORK: Complete assignments for other classes. Begin mummy wing animation, and import scene to Houdini for smoke and torch fire fx.

THURS, APR 24

WORK: Continue animating smoke and fire. Set up render takes in Houdini.

FRI, APR 25

WORK: Continue animating smoke and fire. Complete a test render.

SAT, APR 26

WORK: Savannah Sidewalk Art Festival. Day off to complete assignments for other classes.

SUN, APR 27

Makeup day.

WEEK 6: ANIMATION/FX

MON, APR 28

WORK: Continue working on all animation based on critique. Complete assignments for other classes.

TUES, APR 29

WORK: TECH 311 Project 2 due. Continue working on FX and complete a full test render. Resume work on wing animation.

WED, APR 30

WORK: Continue animation work based on critique.

THURS, MAY 1

WORK: Out to Launch. Refine camera animations from animatic.

FRI, MAY 2

WORK: Out to Launch. Continue animation work, complete a full render of shots 3 and 4.

SAT, MAY 3

WORK: Finalize animations. Complete assignments for other classes.

SUN, MAY 4

Makeup day. ENG 168 Essay 1 due.

WEEK 7: LIGHTING

MON, MAY 5

DUE: Assign 4, all animation, FX.

WORK: Day off.

TUES, MAY 6

WORK: Develop lighting for shot 1 (flickering torches).

WED, MAY 7

WORK: Continue work on lighting based on critique. Complete assignments for other classes.

THURS, MAY 8

WORK: Begin work on sarcophagus lighting (light rays).

FRI, MAY 9

WORK: Coninue working on all lighting.

SAT, MAY 10

WORK: Complete assignments for other classes. Finalize all lighting, complete a full render of entire project.

SUN, MAY 11

Makeup day.

WEEK 8: COMPOSITING

MON, MAY 12

WORK: Tweak based on critique; complete a full render for rough cut. Add placeholder sounds.

TUES, MAY 13

WORK: TECH 311 Project 3 due.

WED, MAY 14

DUE: Assign 5, rough cut, 75% completion.

WORK: Complete assignments for other classes. Set up Nuke node network with render passes.

THURS, MAY 15

WORK: Develop compositing.

FRI, MAY 16

WORK: Develop compositing.

SAT, MAY 17

WORK: Complete assignments for other classes. Develop compositing.

SUN, MAY 18

Makeup day.

WEEK 9: COMPOSITING/SOUND DESIGN

MON, MAY 19

WORK: Continue working on compositing based on critique.

TUES, MAY 20

WORK: Continue compositing, complete full render.

WED, MAY 21

WORK: Complete assignments for other classes. Continue compositing based on critique.

THURS, MAY 22

WORK: Continue compositing, begin sound design.

FRI, MAY 23

WORK: Continue compositing and sound design.

SAT, MAY 24

WORK: Complete assignments for other classes. Finalize compositing and sound design.

SUN, MAY 25

Makeup day. ENG 168 Essay 2 due.

WEEK 10: FINAL TOUCHES

MON, MAY 26

WORK: Make presentation, final touches on sound/compositing from critique.

TUES, MAY 27

WORK: Final touches from critique.

WED, MAY 28

DUE: Final Assets, Final Presentation.

THURS, MAY 29

WORK: TECH 311 Project 4 due.

FRI, MAY 30

SAT, MAY 31

Graduation!!